Data Centers Are Coming to Will, DuPage & Grundy Counties

What we know, what we don’t, and how to be heard before the vote · August 2026

Download full report (PDF) Print the one-page flyer (PDF)
Watch the whole thing · 2 min 51 sec · Captioned on screen, so it can be watched with the sound off. Project statuses shown as of September 2026.

The bottom line, up front

  • At least ~3.1 gigawatts of data-center power is already proposed across our three counties — more than the entire Dresden nuclear plant produces.
  • The idea that these projects will “provide their own power” is not true. Public filings show they draw that power from the ComEd grid — the same grid forecast to run short by 2029.
  • The idea that they will “pay for their own water” is unproven. One project (Joliet) disclosed low, closed-loop water use; another (Morris) has the city looking at building new water facilities; and Illinois has no law requiring data centers to even report their water use — all on an aquifer that is already being drained.
  • The one moment residents have real leverage is before a project is approved.
Bar chart: proposed data centers 3.1 gigawatts versus Dresden nuclear plant 1.8 gigawatts
Just three confirmed projects would need about 1.7× the entire output of the Dresden nuclear station in Grundy County.

What’s being proposed

These are the larger projects that are public. There are almost certainly more — many are filed under shell companies with code names, so even a complete count is hard to get.

CountyProject / DeveloperPowerStatus
WillJoliet Technology Center — PowerHouse + Hillwood (795 acres, 24 bldgs)1,800 MWApproved
GrundyMorris Technology Park — Tract (343 acres, 2.9M sq ft)1,000 MWProposed
GrundyCoal City Campus — Aligned (11 buildings, ~300 acres)not disclosedProposed
GrundyGrundy site — Cielo Digital300 MWProposed
DuPageWood Dale — CyrusOne (6 buildings, ~1.4M sq ft)not disclosedIn development
DuPageLisle, Itasca (NTT), Carol Stream — smaller sites~50 MW & lessProposed / building

Claim 1: “They’ll provide their own power.” Not what the filings say

The projects do not build their own power plants. They connect to the ComEd electric grid — the same grid that serves your home:

And the grid is already tight. PJM (our regional grid) could be about 15 GW short of power by 2030, and ComEd forecasts shortfalls in northern Illinois by 2029. Regulators found that about 70% of this year’s regional electricity-cost increase came from data-center demand — a cost shared by all ratepayers, including you.

Claim 2: “They’ll pay for their own water.” Partly true, mostly unproven

Why are these being built — and what if the demand doesn’t come?

These campuses are not mainly for training AI models — they are for running them for users. The industry is betting that demand will explode as AI “agents,” reasoning models, and video generation use far more computing power per task, and as AI gets built into more products.

But much of this is a speculative race. Every company is adding capacity on the assumption the demand will arrive. If it doesn’t — or if AI never earns back its enormous cost — a community can be left holding the water use, the grid strain, and the tax breaks for buildings that sit half-empty or are abandoned. That is exactly why the decommissioning bond and rate-protection conditions below matter: they protect you if the boom does not last.

How big a problem is this really?

The power problem is large and confirmed. The water problem is real but depends on the project — and sits on an aquifer that is already failing.

Why so much of this is hard to find out

Several rows in the table above say “not disclosed.” That is not a gap in our research — it is how these deals are structured.

Across the country, data-center developers routinely ask city and county officials to sign non-disclosure agreements before negotiations even begin. In Virginia, one review found roughly 80% of localities with proposed or existing data centers had them. What those agreements typically cover is precisely what a resident would want to know before a vote:

Projects are also commonly filed by shell companies under code names, so even the developer’s identity can stay unclear until late in the process. The practical effect is that a handful of elected officials may hold information their constituents cannot see — and may not be free to discuss it at the hearing where the vote is taken.

There is a bill about exactly this — and it has not passed

Illinois SB 4016 (Sen. Ram Villivalam, introduced February 2026) would prohibit non-disclosure agreements for data-center projects, and require cumulative impact assessments, public notice, and community benefits agreements.

The General Assembly adjourned its spring session without passing it, or the related POWER Act. In response, Gov. Pritzker paused new Data Center Investment Program tax-incentive agreements effective July 1, 2026, and asked lawmakers to build a comprehensive framework during the veto session this fall.

That session is the next real opening. If you contact a state legislator about anything on this page, SB 4016 is the bill to name.

What residents can ask for — before the vote

The state declined to set rules, so the only real leverage is at the local approval hearing. Once a project is approved, the binding numbers move to other agencies where there is no public vote. Before approval, residents and officials can ask that these be made conditions of approval, in writing:

Who decides — and how to be heard

Data centers usually need a special-use permit. Who votes on it depends on whether the site sits inside a city/village or on unincorporated county land — but in both cases, the public may speak at a hearing before the vote.

Make your voice count — before the vote

Attend the Zoning Board of Appeals or Plan Commission hearing, and contact your County Board member (unincorporated land) or your Mayor and City Council / Village Board (city or village) to ask for the protections above. Share this page with neighbors.

Where these numbers come from

  1. Joliet Technology Center approval, 1.8 GW, water and closed-loop disclosure: Shaw Local / The Herald-News; Data Center Dynamics.
  2. Tract Morris Technology Park, 1 GW, FERC-approved ComEd transmission agreement (Apr 20, 2026): Data Center Dynamics; The Real Deal Chicago.
  3. Aligned Coal City and Cielo Grundy projects: Village of Coal City; Cleanview; WCSJ News.
  4. PJM grid shortfall (~15 GW by 2030), ComEd shortfalls by 2029, 70% of cost increase from data centers: PJM Independent Market Monitor; Citizens Utility Board; ArentFox Schiff; Introl.
  5. Aquifer depletion and the $1.5B Lake Michigan pipeline: Illinois State Water Survey; Great Lakes Now; Inside Climate News.
  6. Failed Illinois water/energy disclosure law: Circle of Blue. Data-center NDAs with local governments, and the Virginia 80% figure: Public Citizen, The Secret Data Center Buildout; Federation of American Scientists. SB 4016 text, sponsor and status: Illinois General Assembly. Data Center Investment Program pause effective July 1, 2026, and the call for a veto-session framework: Office of Gov. JB Pritzker.
  7. Dresden nuclear output (~1,845 MW) and 2025 license renewal: Constellation Energy; U.S. Nuclear Regulatory Commission.